Water-rich sand cross passage: 3 mm settlement, 6 days ahead

A metro cross passage in East China crossed water-rich fine silty sand. With high permeability, plain bentonite slurry lost over 15 L/min; the failed wall triggered surface settlement and a 5-day stoppage on a schedule-critical section.

Project overview

Region
East
Project type
Metro / shield
Project scale
One metro cross passage on the line's critical path, beneath a city road

Construction challenges

The main construction challenges encountered on this project.

Challenge 1Heavy loss

Permeable silty sand pushed plain slurry loss beyond 15 L/min, consuming material fast.

Challenge 2Settlement sensitive

A city road sat overhead with a 10 mm settlement control line.

Challenge 3Tight schedule

The cross passage governed the whole line — breakthrough could not slip.


Solution & materials

Materials and mix ratios used step by step on this project, for reference by similar works.

StageMaterialFunctionRatio / dosage
Mix designPAM-SFilm-forming main material1:400
Crossing sectionPAM-S concentrated slurryReinforced protection1:250
Base slurryBENT-NBase make-up8%
MaintenanceCompound top-upRe-viscosify by return testsAs required

Implementation notes

PAM-S film-forming slurry replaced the original bentonite mix, with a 1:250 concentrated section through the crossing. The film formed quickly on the sand wall, cutting loss from above 15 L/min to under 2 L/min. With staged top-ups and monitoring, peak settlement reached just 3 mm and breakthrough came 6 days early with 100% hole acceptance.


Delivered results

3mm
Settlement control
6 days
Ahead to breakthrough
How results were verifiedSurface settlement monitoring, on-site slurry loss testing and bore acceptance records


Related products

GET A QUOTE

Tell us your strata conditions —
get tailored selection advice

Share your strata, borehole diameter and schedule; engineers will reply with mix advice, quantity estimates and lead time. Your information is used only for this enquiry.

✓On-site strata compatibility assessment (per project arrangement)
✓Batch test report & certificate with every shipment
✓On-site mix commissioning by our engineers (per project arrangement)
✓Samples and product brochures on request
Sales hotline
Business email
Form mode
For a quick conversation, leave your name, phone and a short message. Choose detailed project requirements if you have strata, borehole diameter or schedule data.
Filled in from the entry point you used; you can change it
Additional strata (multiple choices)
We will contact you to discuss your requirements.